EVSE mounting for solid-wall construction
To secure the unit in concrete, pre-drill appropriately sized holes and use multi-set or wedge anchor hardware
at both mounting points.
To secure the unit in brick or stone, pre-drill appropriately sized holes and use sleeve anchors at both mounting
points.
The included plastic angle washers can be oriented to allow bolts to be fastened either at an angle or perpendicular
to the mounting surface.
NOTE: There are two dierent sets of plastic angle washers included. Select those washers that best accommodate the
mounting hardware
angle of attack
and orient them
accordingly.
NOTE: If the head of the mounting hardware is smaller than the
⅜"
(1 cm)
plastic angle washer aperture, an additional
at washer will need to be placed between the plastic angle washer and the mounting hardware.
Machine screw size ¼
"
- 20 hardware is recommended for mounting the EVSE. Screw shafts of at least 2
"
(5.1 cm)
are recommended. The EVSE plastic angle washer hole size is
⅜"
(1 cm) in diameter. Ensure the screw heads are of
a larger diameter. Place appropriately sized washers between the screw heads and the HCS enclosure mounting
anges.
Figure 10: Mounting the EVSE to a solid wall
17"
Solid wall mounting (ush)
Longer