3.3.2 Charger foundations WITHOUT Auxiliary power cabinet (APC):
The different steps of installation are:
Step 1:
- Dig a hole at selected location of minimum dimensions on the plan (> 720 mm x > 410
mm). The disbursement depth should be greater than 700 mm. Don’t forget to allocate
room for the cables passage indicated in APPENDIX 2.
Step 2:
- Place and lock the clamping/sealing kit with regards to the specified measures as shown in the next
drawing. With no clamping kit available, lock the equipment to ground using chemical sealant.
The clamping kit has a specific mobile metal sheet (upper sheet) to tune the ground level
whenever necessary.
> 720 mm
> 410 mm
Cable input
Deep 700 mm
Rear side
Front side
Front side
2
1
3