07-20-00 SHORING
Shoring the Extra 300/SC is necessary, when the main
landing gear or the tail wheel has to be removed or installed.
07-20-01 Shoring the Front
1 Remove the fore access panels up to aft the main landing
gear as per Chapter 51-00-01.
2 Install a balance weight (3, Figure 2) at the tail as per
Chapter 07-10-01.
3 Hoist the aircraft by means of both engine hoisting points
(1).
N O T I C E Prevent damage of ventilation tubing, brake lines and
center tank drain, when shoring the aircraft.
4 Shore the aircraft by means of two supports (2), which
are to put under the left and right bottom longeron each
in the area behind the landing gear as shown in Figure 2.
This is possible also, when the landing gear is installed.
W A R N I N G Maintain hoisting strap as a security device to prevent
nose over of the aircraft during maintenance work.
Shoring the Front
Figure 2