STRADA GENERATION3 – S5 - INSTALLATION MANUAL
30/66
M. When the chemical anchoring is dry, screw 4 M16 nuts (2) on the threaded rods
(1) down to the ground level. Check the horizontal alignment with a spirit level
Installation of the lower nuts
The terminal is installed on the nuts, not on the base.
These 4 nuts that allow the alignment of the terminal are called "lower nuts" in the
rest of this document.
6.2.6 Security after anchoring
While waiting for the terminal installation, Flowbird recommends using an anchoring
protection that can be installed on the threaded rods.
Anchoring protection