STRADA GENERATION3 – S5 - INSTALLATION MANUAL
42/66
H. Fill the base with concrete (6) up to the anchoring brackets (5).
Base in position before exterior finish
I. Respect the drying time recommended by the concrete supplier.
J. Carry out the floor exterior finish (if the finish is concrete or pavement, it is not
necessary to wait for the concrete to dry).
K. When the chemical anchoring is dry, screw 4 M16 nuts (1/4) on the anchoring rods
aligned with the base top and check the horizontal alignment with a spirit level (3).
The terminal is installed on the nuts, not on the base.
Installation of the lower nuts
These 4 nuts that allow the alignment of the terminal are called "lower nuts" in the rest
of this document.