FT-C Vertical Electric Thermal Fluid Heater Manual 12 2013 ISSUE 1



1. The heater system should be shut down after no more than 24 hours of operation at full
operating temperature. At this time, the following maintenance items will need to be completed
to meet warranty conditions.
2. While pump is still at operating temperature, align circulating pump(s) to pump manufacturers
specications. This should be done by means of a dial indicator.
3. Isolate Y-strainer(s) in system and clean regardless of pump suction pressure. Make sure that
the temperature is low enough to handle safely or provision has been made to handle materials
at high temperature. Generally, temperatures below 65°C are acceptable to perform operation
with regular work gloves.
4. With piping system cooled to ambient temperature, torque all bolts on skid and throughout
system to gasket manufacturers specications using proper ange torquing practices such as
incremental torque increases, star pattern, etc. Refer to 
5. Visually inspect all thread ttings and valve packings. Repair leaks and tighten valve packings to
the point of stopping leak.
6. Upon putting unit back into operation, check all gauge readings and compare to values given to
you by the start-up technician. Note any discrepancies and contact Fulton Ltd.
11. If steam is forcing thermal uid out of the expansion tank vent, turn the heater off, but leave
the pump on. This is to circulate the hot uid through the piping without ushing the steam too
quickly. Once steam and thermal uid stop leaving the expansion tank unit, the heater can be
turned on. Increase the temperature very slowly to prevent uid from being forced out of the
tank.
12. Continue bringing unit up to temperature slowly, with a temperature rise not exceeding 100°F
(38°C) per hour. Do not exceed specied maximum outlet temperature. In the absence of
specic information, consult the factory before proceeding.
13. Once up to temperature, check the uid level in the expansion section by opening the high
level manual test connection. If a permanent ow of uid results when this valve is opened, and
if all previous precautions have been followed, the expansion tank is too small for the capacity
of the uid in the installation. A larger tank must be installed.
14. After fty hours of operation at operating temperature, check all anges and connections for