Chapter 3
Transportation, Shipment and Storage
3.1 Machine tool transportation
Spare trucks transport to the final installation site, the work must be
conducted by users in the preparation and implementation. Must be
declared machine in time before delivery to the installation place of course.
In particular, to the doorway pillar size, height can use armoured cable
bracket height, pavement roller, etc.
Must consider the scale of the machine tool drawings marked in transit!
Assist and handling tools
The user must prepare for the following items:
1. Used for machine tools, laser and additional devices of truck crane.
Suggestions for the lifting force for at least 80 t hydraulic crane; If according to
the local situation need to use a bigger boom, truck crane must have greater
gravity.
2. Forklift (2.5 t) bearing capacity.
3. The bearing capacity of bridge crane: 10 t 4.Armoured roller (1 and 2 can be
turned to a solid).
4.At least two lifting force for at least 5 t (30 mm) minimum height adjustable rear:
hydraulic jack.
Picture 3-1 Forklift drawings
Note:When the machine are transport to the installation point,the distance between