Rads/UFH
Has all air been vented from radiators
Have all radiators been balanced
If underfloor, have all correct flowrates been set
Are all actuators and wiring centres been fully wired and connected
Electrical
Has correct size RCBO been fitted to heat pump supply
Has external isolation switch been secured beside heat pump
Has correct size mains cable been used
Has correct size cable been ran from heat pump to wiring centre
Has correct sized cable been ran from heat pump to controller
Have all cables been ran from motorised valves/underfloor wiring centres
etc to Grant wiring centre
Has correct size cable been ran from board to immersion
Has time boost kit been wired into immersion supply
Has cylinder stat been fitted and wired back to Grant wiring centre
Are all connections been correctly made in Grant wiring centre
Are all heating controls fully wired and working
Are all underfloor stats wired back to corresponding actuators