    96   
the unit cannot properly run. 
③ Before commissioning is completed, the main board of ODU displays "module address 0F A0" 
and that of IDU displays “A0”. 
④ A module must be set to master module and only one can be set during commissioning. 
⑤ An IDU must be set to master IDU and only one can be set during commissioning. 
⑥ Other functions can use the factory settings if there are not special engineering requirements. 
3.1 Necessity of VRF Engineering Commissioning 
Different form ordinary air conditioning units, the VRF system raises high design requirements and 
easily incurs operation-affected factors such as impurities and water during engineering installation. Due 
to  the  requirements  on  engineering  design/installation  complexity  and  high-precise  system  control, 
commissioning is mandatory after engineering installation. Only a qualified unit can be delivered for use. 
3.2 Required Files and Tools for Engineering Commissioning 
3.2.1 Required Tools for Engineering Commissioning of GREE VRF 
The  GMV5E  VRF  provides  two  commissioning  methods.  One  is  to  perform  commissioning  by 
pressing buttons on the main board of ODU. The other is to perform commissioning on a PC through 
professional software. Parameters of the ODU and IDU can be simultaneously displayed with the second 
method. (For details about these methods, refer to respective instructions.) 
3.2.2 Commissioning Files 
The following commissioning files are required to record installation and commissioning of units: 
pre-commissioning  scheme  determination  meeting  minutes,  commissioning  personnel  record  tables, 
commissioning  system  appearance  check  record  tables,  commissioning  data  record  tables,  and 
commissioning reports. See attached tables for file formats. 
3.3 Engineering Commissioning Procedures 
3.3.1 Step 1: Pre-commissioning Preparations 
3.3.1.1 Overall Commissioning Plan 
Before commissioning, the person-in-charge should learn about the overall engineering progress 
plan,  overall  workload  of  engineering  commissioning,  possible  influence  factors  in  achieving  the 
commissioning progress, and required labors and materials. 
3.3.1.2 Composition of Commissioning Members 
Commissioning members comprise aftersales commissioning personnel and installation personnel.