4 Requirements on Foundation Installation 
4.1 ODU Foundation 
The concrete foundation of the ODU must be strong enough. Ensure that the drainage is smooth 
and that the ground drainage or floor drainage is not affected. 
Requirements on the concrete foundation are as follows: 
A. The concrete foundation must be flat and have enough rigidity and strength to undertake the 
unit’s  weight  during  running.  The  height  of  the  foundation  is  200  mm  to  300  mm,  which  is 
determined based on the size of the unit.   
B. The proportion of the cement, sand, and stone for the concrete is 1:2:4. Place 10 reinforced steel 
bars (φ10 mm) with a space between of 30 mm. 
C. Use the mortar to flatten the surface of the foundation. Sharp edges must be chamfered. 
D. When  the  foundation  is  built  on  a  concrete  floor,  crushed  stones  are  not  required.  But  the 
foundation surface must be roughened.   
E. Clear the oil stains, crushed stones, dirt, and water in the reserved bolt hole of the foundation and 
install a temporary cover before installing bolts. 
F. Build a drainage ditch around the foundation to discharge the condensate water. 
G. If  the  air  conditioner  is  installed  on  the  roof,  check  the  intensity  of  the  building  and  take 
waterproof measures. 
H. 
If  a  u-steel  foundation  is adopted,  the structure  must be  designed  with sufficient rigidity  and 
strength.
 
Anchor bolt with a nominal 
diameter of 12 mm
Minimum width: 100 mm
Proportion of the cement, sand, and 
stone for the concrete is 1:2:4.
Drain tank: 100 mm×20 mm
This distance is determined based on the actual size of the unit.
Cement foundation diagram
200 mm~300 mm
30 mm