1.4 Onsite Review of Design Drawing 
Installation  personnel  must  carefully  read  and  understand  the  design  scheme  and  drawings 
provided by engineering designers, and prepare detailed and feasible construction organization design 
after reviewing the onsite status.   
The following aspects of working drawing must be reviewed: 
1. The loads of indoor and ODUs must match. The gross rated capacity of the IDU should be set to 
a value that is 50% to 135% of the rated capacity of the ODU. In actual conditions, if the capacity 
of  concurrently  operating  IDUs  exceeds  100%  of  the  rated  capacity  of  the  ODU,  the  air 
conditioning system fails to meet the requirement. Note: Configuration in excess of the capacity 
of the IDUs can affect the comfort for users. The more the excess is, the lower the adjustment 
capacity of an air conditioning unit will be. When the capacity exceeds 135% of the configured 
value, the system reliability can be affected. Therefore, relevant regulations on capacity limit must 
be strictly followed.   
2. The difference of level between an ODU and an IDU, and that between IDUs must be set within 
the designed range.   
3. Pipe bend for trapped oil is required for air pipe riser in the unit to ensure normal circulation in the 
unit lubricating system.   
4. The  pipe  diameter  and  manifold  type  in  the  cooling  system  must  meet  relevant  technical 
specifications.   
5. The  drainage  method of  unit condensate  water  must be reasonable;  the pipeline  slope must 
follow the design requirement of unit.   
6. The air duct direction and air flow are reasonably organized.   
7. The  configuration  specifications,  type,  and  control  method  of  power  cables  should  meet  the 
design requirement of unit. 
8. The  arrangement,  total  length,  and  control  method  of  control  line  should  meet  the  design 
requirement of unit. 
Note: 
Engineering construction personnel must strictly abide by the design drawings. If any design 
cannot be  implemented during  construction  and needs  to be modified,  contact the  designer  first for 
approval and prepare a written document, that is, the design modification record.