Step 4: On the engineering debugging page, click “Startup” button to start engineering debugging; 
press “Stoppage” button to pause the engineering debugging; 
 
Step  5:  Once  it  entered  the  engineering  debugging,  Portable  Commissioning  Tool  will  display 
current progress of engineering debugging (step#). As for step 3, 4, 8 and 12,   
it needs to click “OK” button to enter into the next step debugging. “Skip” can be selected for step 10. 
Detailed information check is available for step 3, 4, 5, 6 and 7. 
Step 6: Once engineering debugging is finished, the outdoor unit displays 01 AC or AH OF (or error 
code when there’s malfunction; on is displayed when the unit is displayed) 
Warning: 
After  finishing  operating  this  product,  the  wiring  of  air  conditioner  must  be  resumed. 
Otherwise, it may affect the actual operation of user! 
3.3.3.3 Operations after Commissioning 
Sort  and  save  data.  Make  detailed  records  of  exceptions  and  troubleshooting  methods  during 
commissioning for later maintenance and query. At last, make a commissioning report and hand it over 
to users. 
3.3.3.4 Precautions to Let Users Know after Commissioning 
① Let users know where the master IDU is located and stick a label to the master IDU. Tell users 
that modes of other IDUs are limited by the mode of master IDU. 
② An ODU that has been in power-off status for more than 24 hours should be preheated for more 
than eight hours before startup to prevent damaging compressors. 
3.4 References for Proper Unit Operation Parameters 
●When the system compressor is running, the 
normal discharge pipe or top temperature for cooling 
is 70-95°C, which is more than 10°C higher than the 
saturation temperature corresponding to the system 
high-pressure. The normal temperature for heating