Transport,installationandstart‐up
 
UsermanualforHONR100gaspressureregulatorwithHONP095NGpilot  35
 
Conductafinalinspectiontocheckwhetherthefollowingcriteriaaremet:
  Allscrewedconnectionsonthedeviceandsupplylinesaresecurelyfastened.
If… then…
atleastonecriterionisnotmet,
youshouldcorrecttheerrorbeforeproceeding
withthenexttask.
allcriteriaaremet, youmayproceedwiththenexttask.
Proceedasfollows:
Installingthedeviceconnections(seepage35)
5.3  Installingthedeviceconnections
Someofthemeasuringimpulselineswillcomepre‐installed:
Figure No. Designation, 
category, 
installationcondition
Front:
Back:
1 Motorizationline
Operatingline
pre‐installed
2 Outletpressuremeasuringline
Operatingline
needstobeinstalled
3 Outletpressuredischargingline
Operatingline
needstobeinstalled
4 Inletpressureline
Operatingline
needstobeinstalled
5 Outletpressurefeedbackline
Operatingline
needstobeinstalled
6 Outletpressureline
Operatingline
needstobeinstalled
Preparethefollowingmaterials:
  Pipes,connectingpieces,andfittingsasperthespecificationsintheTechnicalspecifica‐
tions(seepage17)
  Shut‐offdevicesfortheoperatingandmeasuringlines,aswellasotheraccessories,as
required,aspertheBasicsforinstallingthedeviceinapipe(seepage25)section.
Theinstallationoftheoperatingandmeasuringlinesdependsonthelocalconditionsandthe
gasregulatinglineinwhichthegaspressureregulatorisbeingused.PleaserefertotheBasics
forinstallingthedeviceinapipe(seepage25)sectionformoreinformationonwhatneedsto
beensuredwithoutfailinthecorrespondingdesignandimplementation.
Finalinspection
Nexttask
Operatingandmeasuring
linesthatare
pre‐installedandthat
needtobeinstalled
Preparingthematerials
Installingtheoperating
andmeasuringlines