7.2.4.3 Installing the Ball Bearing Rail Kit
The ball bearing rail kit applies to cabinets with a distance of 610 mm to 914 mm
(24.02 in. to 35.98 in.) between the front and rear mounting bars.
The 2288X V5 servers are stackable onto the ball bearing rail kit.
Procedure
Step 1 Push the release latch on the front of the rail and pull out the hook. See (1) and
(2) in Figure 7-7.
Step 2 Insert the positioning pin at the rear of the rail into the hole on the rear post of
the cabinet. See (3) in Figure 7-7.
Step 3 Keep the rail horizontal, and push the front end of the rail until it is inserted into
the hole on the front post of the cabinet. See (4) in Figure 7-7.
Step 4 Hook the rail. See (5) in Figure 7-7.
FusionServer Pro 2288X V5 Server
User Guide 7 Installation and Conguration
Issue 04 (2020-06-05) Copyright © Huawei Technologies Co., Ltd. 76