6 Power-On Commissioning
● Ensure that all the preceding items are checked and meet requirements
before power-on.
● The Smart PCS can be commissioned using the SmartLogger WebUI or the
SUN2000 app. You can manage multiple devices on the SmartLogger WebUI.
For details, see the
SmartLogger3000 User Manual.
You can locally access
devices on the app to modify parameters or upgrade software of a single
Smart PCS.
● For details about how to commission the Smart PCS and the ESS together, see
the
LUNA2000-200KWH-2H1 Smart String Energy Storage System User
Manual
.
Indicator Description
You can view the running status of the Smart PCS by observing the LED indicators
on the panel.
Figure 6-1 LED indicators
LUNA2000-100KTL-M1 Smart Power Control System
User Manual 6 Power-On Commissioning
Issue 02 (2023-01-10) Copyright © Huawei Technologies Co., Ltd. 48