7 Verifying the Installation
After the installation is complete, check the items listed in the following tables.
Perform the power-on operation only after all items are
veried.
Table 7-1 Checking hardware installation
No. Expected Result Check Result
1 The cabinet is clean, without redundant screws,
copper wires, or other debris.
□ Passed □
Failed
2 The paint on the cabinet exterior is intact. □ Passed □
Failed
3 The cabinet door and lock work properly. □ Passed □
Failed
4 All safety marks and warnings are correct, clear, and
complete.
□ Passed □
Failed
5 There are no sundries such as adhesive tape, cable
tie, paper scrap, or packing material around the
cabinet.
□ Passed □
Failed
Table 7-2 Checking electrical connections
No.
Expected Result Check Result
1 All cables are securely connected. □ Passed □
Failed
2 Ground cables are securely connected. □ Passed □
Failed
3 Power cables and ground cables are not coiled and
extra parts are cut o.
□ Passed □
Failed
4 The phase sequence is correct. □ Passed □
Failed
PDU8000 DC Combiner Cabinet
Quick Guide 7 Verifying the Installation
Issue 02 (2022-08-10) Copyright © Huawei Digital Power Technologies Co., Ltd. 28