PowerCube 5000 (SUN2000-150KTL-S0)
Installation Guide
9 Power-on and Commissioning
Copyright © Huawei Technologies Co., Ltd.
NOTE
Configurable range: ±5% of the present voltage
level
Set based on site requirements.
NOTE
Configurable range: 50/60
Set based on site requirements.
NOTE
Configurable range: 0–1000, 1000–2000,
2000–3000 or 3000–4000
Set based on site requirements.
NOTE
This parameter is displayed only when a
parallel system is used.
Configurable range: Start
If the power cabinet is not powered on for the
first time and the cable connection is
changed, choose Micrgrid System >
Monitoring > Running Control, and set AC
Phase Sequence Detect to Start on the
WebUI.
If the detection result is abnormal, alarms AC
Input Phase Sequence Incorrect and AC
Output Phase Sequence Incorrect will be
generated on the MDU and WebUI. In this
case, reconnect the cables.
6. Set the System Param. 4.
This parameter is displayed only when the number of DGs is set to 1.
Table 9-6 Setting the System Param. 4
Set based on site
requirements.
DG Limited Power Point
(%)
Set based on site
requirements.
7. Set the Network Param.