1.3 Transportation, Unpacking, and Checking
NO TICE
Only trained personnel are allowed to move the device.
Do not transport the device by holding the mounting ears, front panel, or
wiring protective cover.
To prevent the device from falling over, secure it to a pallet truck using ropes
before moving it. Move the equipment with caution to avoid bumping or
falling, which may damage the equipment.
After placing the equipment in the installation position, unpack it and take care
to prevent scratches. Keep the device stable during unpacking.
Before unpacking batteries, check whether the packaging is intact. Do not use
batteries with damaged packaging. If any damage is found, notify the carrier
and manufacturer immediately.
After unpacking, check whether the fastening components and removable
components are loose. If they are loose, notify the carrier and manufacturer
immediately.
If the installation environment is poor, take dustproof and anti-condensation
measures (for example, use a dust cover, plastic
lm, or fabric cloth) after
unpacking batteries to prevent condensation and dust buildup, which may
corrode the batteries.
Step 1 Verify that the battery packaging is intact. If any damage is found, notify the
carrier immediately.
Step 2 Move the device to the specied position.
Step 3 Unpack the battery module and place it in a dry indoor environment without
corrosive gases.
Step 4 Check whether the device is intact.
1. Visually inspect the battery appearance for shipping damage. If any shipping
damage is found, take photos and notify the carrier immediately.
2. Check whether the models of the accessories are complete and correct. If
there is any discrepancy, keep a record and contact the supplier immediately.
----End
1.4 Installing Battery Modules
D ANGER
Ensure that the site is equipped with qualied re extinguishing facilities, such as
reghting sands and carbon dioxide re extinguishers.
SmartLi-ESM-24020P1
Quick Guide 1 Installation and Cable Connection
Issue 03 (2022-12-30) Copyright © Huawei Digital Power Technologies Co., Ltd. 8