Figure 1-25 Installing a communications cable between the battery module and
the UPS
(1) UPS (2) Battery module
Step 2 If multiple battery modules are cascaded in a string, install parallel cables for the
battery modules.
Figure 1-26 Installing parallel cables between battery modules
NO TICE
Do not use a parallel cable to directly connect the UPS to the battery parallel port.