INSTALLATION
Independent - Installation and Servicing
28
COMMISSIONING AND TESTING
GENERAL
Please Note: The combustion for this appliance has
been checked, adjusted and preset at the factory for
operation on the gas type dened on the appliance
data plate. DO NOT adjust the air/gas ratio valve.
Having checked:
- That the boiler has been installed in accordance
with these instructions.
- The integrity of the ue system and the ue seals,
as described in the Flue Installation section.
Proceed to put the boiler into operation as follows:
CHECK THE OPERATIONAL (WORKING) GAS
INLET PRESSURE
Set up the boiler to operate at maximum rate by
opening hot tap to maximum ow.
With the boiler operating in
the maximum rate condition
check that the operational
(working) gas pressure at
the inlet gas pressure test
point complies with the
requirements - refer to “Gas
Supply” on page 8.
Ensure that this inlet pressure
can be obtained with all other
gas appliances in the property
working.
Safety
Drain
Valve
Black
Handle
Yellow
Handle
Black
Handle
Blue
Handle
3G9927
CH Flow
DHW Outlet
Gas Supply
CH Return
DHW Inlet
Gas Pressure
Test Point
WARNING. Whilst effecting the required gas tightness test and purging air from the gas installation,
open all windows and doors, extinguish naked lights and DO NOT SMOKE.
A. Electrical Installation
1. Checks to ensure electrical safety should be carried out by a
competent person.
2. ALWAYS carry out the preliminary electrical system checks, i.e.
earth continuity, polarity, resistance to earth and short circuit,
using a suitable test meter.
3. After wiring the boiler, all grommets in the bottom panel MUST
be in place to ensure that the boiler case sealing is maintained.
B. Gas Installation
1. The whole of the gas installation, including the meter,
should be inspected and tested for tightness and purged in
accordance with the recommendations of BS. 6891.
In IE refer to IS.813:2002.
2. Purge air from the gas installation by the approved
methods only.
ATTENTION !
IT IS A CONDITION OF THE MANUFACTURERS WARRANTY THAT THE
BENCHMARK COMMISSIONING CHECKLIST IS FULLY COMPLETED
AND LEFT WITH THE APPLIANCE
As part of the commissioning process, the combustion of this appliance must be checked
and the Benchmark Checklist completed. A ow chart to assist is provided on page 63.
INSTALLATION

Other manuals for IDEAL C24

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IDEAL C24 and is the answer not in the manual?

IDEAL C24 Specifications

General IconGeneral
BrandIDEAL
ModelC24
CategoryBoiler
LanguageEnglish

Related product manuals