Page #13 background imageLoading...
Page #13 background image
13
EVOMAX -
Installation & Servicing
INSTALLATION
RF 5755
RF 5756
12
HORIZONTAL WALL FLUE KIT
Contents
Boiler adapter + screws (x6)
90
o
elbow
Terminal
Locking collars (x2)
Wall plates (x2)
13
HORIZONTAL WALL FLUE KIT - 
Contents
Boiler adapter + screws (x6)
Increaser
90
o
elbow
Terminal
Locking collars (x2)
Wall plates (x2)
11
FLUE SYSTEMS
A comprehensive range of ue kits are available from
Ideal Stelrad Group. Examples of horizontal and vertical
concentric and open ue options are demonstrated on the
following pages. Tables are provided with these examples,
giving the maximum extensions which may be added. The ue
lengths achievable without any extensions are also provided.
For horizontal ues: this is the distance from the ue outlet
centre line on the boiler to the outside wall. Horizontal ues are
not available for Evomax 150.
For vertical ue: this is the distance from the top of the boiler
case to the aperture in the weather collar.
If elbows are to be used, then the equivalent length of that
tting (see page 17) must be subtracted from the maximum ue
extensions allowed for that ue option.
Note: Horizontal terminal resistance includes 1 x 90
o
elbow.
Worked examples are shown on page 17 and 18.
Alternatively the resistances of ue components are given
on page 16, together with the maximum ue resistance each
boiler can work against. These may be used to calculate the
total ue resistance of the system, and to determine if they are
acceptable to run on the boiler.
Multiple boilers may be installed with a common ue header
(not supplied by Ideal Heating). The ue system should be
designed and supplied by a specialist ue company. BS 6644
and IGE UP/10 provide guidance on design and the drainage
of condensate from ue stack and headers. Condensate from
a ue stack and header must be collected and drained before
entering the boiler.
Note: See Frame 18 for elbow equivalent lengths.
Note: See Frame 18 for elbow equivalent lengths.
FLUE OUTLET

differentials
Model 30/30P 40/40P 60/60P 80/80P 100 120
Max ue length (m) 42 42 7.5 12 20 17.6
Max ue press diff (Pa) 140 200 117 260 220 288
Flue Size 80 / 125 100 / 150
Wall ue kit No 158659 158661

longer length
Model 60/60P 80/80P
Max ue length (m) 30 35
Max ue press diff (Pa) 133 250
Flue Size 100 / 150
Wall ue kit No 158660
206210-3.indd 13 09/06/2011 13:34:18

Other manuals for IDEAL Evomax 120

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IDEAL Evomax 120 and is the answer not in the manual?

IDEAL Evomax 120 Specifications

General IconGeneral
BrandIDEAL
ModelEvomax 120
CategoryBoiler
LanguageEnglish

Related product manuals