429 Keysight CXG, EXG, and MXG X-Series Signal Generators Service Guide
Functional Tests
Before Performing a Functional Test
Before Performing a Functional Test
1. Ensure that you have the proper test equipment.
2. Switch on the unit under test (UUT) and let it warm up (in accordance with
warm-up requirements in the instrument specifications).
3. Allow sufficient warm-up time for the required test equipment (refer to
individual instrument documentation for warm-up specifications).
Functional test accuracy depends on the precision of the test equipment
used. Ensure that all the test equipment is calibrated before running a
functional test.