55
Step 7
Create a temporary working platform
by placing sturdy planks of a KRAUSE
Teleboard (telescopic aluminium board,
prod no. 122247, see picture) in the
frame. Have two diagonal braces
handed up to you
Note:
To erect and dismantle the scaffold,
you must install temporary working
platforms. These platforms are made
from planks and must be removed
after completion of the installation
or disassembly. According to
DIN EN 12811-1, the planks used for
temporary work-ing platforms must
have a width of minimum 20 cm and
a thickness of minimum 4 cm. They
must extend by at least 50 cm on
both sides of the scaffold.
Step 8
Ensure that you are standing safely and
have the board handed up to you.
To prevent accidents, place the board
on the temporary working platform
before lifting it further.