National Crane Published 03-18-2019 Control # 582-04 4-11
NBT30H-2 OPERATOR MANUAL SET-UP
4
1. Match the socket, wedge, and clip to wire rope size.
The wire rope must pass through the “go” hole in the
wedge.
It must not pass through the “no go” hole in the
wedge.
2. Align the live end of rope, with center line of pin.
3. Secure dead end section of rope.
4. Tighten nuts on clip to recommended torque.
5. Do not attach dead end to live end or install wedge
backwards.
6. Use a hammer to seat wedge and rope as deep into
socket as possible before applying first load.
FIGURE 4-6
Torque Value Table
Cable Size (inches) 3/8 7/16 1/2 9/16 5/8 3/4 7/8 1 1-1/8 1-1/4
Torque lb-ft 45 65 65 95 95 130 225 225 225 360
Torque values shown are based upon clean dry threads free of lubrication.
Terminator Wedge Socket

Table of Contents

Other manuals for Manitowoc National Crane NBT30H-2

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc National Crane NBT30H-2 and is the answer not in the manual?

Manitowoc National Crane NBT30H-2 Specifications

General IconGeneral
BrandManitowoc
ModelNational Crane NBT30H-2
CategoryConstruction Equipment
LanguageEnglish

Related product manuals