3-10 Chapter 3: Installation
Powering Up
This section describes powering up the workstation and the initial
checkout procedures after all hardware has been installed.
Note: No unit setup is required at installation unless the configuration
must be changed from factory defaults. The Wedge Support Disk (LPIN
G370-0701-0000) permits configuration of the operational parameters in
the Wedge.
1. Plug the terminal AC Power Cord into an AC power source.
2. Power on the workstation.