Inspection of the installation
Current regulations require the heating installation to be inspected before it is commissioned. The inspection must
be carried out by a suitably qualified person. In addition, fill in the page for the installation data in the User Manual.
DateSignatureNotesDescription
Ventilation (page 20)
Setting ventilation flow exhaust air
Setting ventilation flow supply air
Connecting ground cables
Heating medium (page 18)
System flushed
System vented
Safety valve
Circulation pump setting
Setting heating medium flow
Boiler pressure
Setting trim valve, number of turns from
closed position
Electricity (page 21)
Connections
Main voltage
Phase voltage
Fuses heat pump
Fuses property
Outside sensor
Room sensor
Current sensor (only copper version)
Safety breaker
Earth circuit-breaker
11Chapter 1 | Important informationNIBE F470

Other manuals for Nibe F470

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Nibe F470 and is the answer not in the manual?

Nibe F470 Specifications

General IconGeneral
TypeExhaust air heat pump
ERP class heatingA++
Energy Efficiency ClassA++
Integrated Hot Water Tank180 liters
RefrigerantR290
ApplicationResidential

Related product manuals