8.
Operation
The VS-5E Series becomes operative when the following 5 operations are performed.
Item Description
1) Switch power ON
2) Set the sensor rotation direction Designate the direction in the angular value increases.
3) Set the origin point
Move the machine to the origin point position, then designate that
position as “zero” at the Controller.
4) Set the switch outputs Set the Switch ON/OFF positions.
5) Run
8-1.
Power ON
The VS-5E Series is not equipped with a power switch. Power ON/OFF switching is executed by an
external switch.
Note: Before switching the power ON, be sure that the wiring is correct, and the terminals are secure.
C-2
Artisan Technology Group - Quality Instrumentation ... Guaranteed | (888) 88-SOURCE | www.artisantg.com

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the NSD Varicam VS-5E Series and is the answer not in the manual?

NSD Varicam VS-5E Series Specifications

General IconGeneral
BrandNSD
ModelVaricam VS-5E Series
CategorySwitch
LanguageEnglish

Related product manuals