3. INSTALLATION & SETUP
This procedure should only be performed by qualified technicians. Incoming steam
lines should be isolated from the steam generator and all lockout/tagout procedures
should be followed.
Connect the drain lines from the steam filter canister and condensation trap to a
suitable drain or condensate return line. Be sure the adjustment knob on the
Armstrong pressure reducing valve is turned to the maximum counterclockwise
position (zero pressure). Connect the steam hose from the output of the steam
regulator to the inlet on top of the tunnel (if shipped separately). Connect a steam
input line from the steam generator to the ball valve located at the steam supply
inlet on the steam tunnel. Connect air line for electronic regulator.
Refer to the installation drawing (in the Assembly Drawings tab of this binder) for
details.