61
12 Initial start-up
Self test When first commissioning a new unit, start a
one-time self-test. This test serves to adjust the
unit to its specific ambient conditions.
It runs automatically, and takes between 45 and
65 minutes depending on the size of the unit; if
an UltraVent is in use, the test will take around
20 minutes longer.
> To perform the self-test, check the hook
latches and the air baffle to ensure they are
seated correctly and no cardboard/plastic is
inside unit.
> The unit must be connected to water, waste-
water, and electricity as per installation
instructions; gas units must also be connect-
ed to gas supply and operational ventilation
hood.
> The left side panel must be closed.
> With tabletop units, insert a flat container into
the middle of the rack, with the opening fac-
ing down.
> With floor units, insert two containers into
the mobile oven rack: one centered in front of
each fan, with the openings facing down.
> Do not open the cooking cabinet door during
the self-test.
> Self-test must not be interrupted, e.g. by
switching unit off.