CleanJet: Error messages - Abort program
Depending on real steam production time or when the scale deposit inside the steam generator is
below 4%, only a small number of Care Tabs is indicated and steps 12, 14, 16 and 19 are skipped (no
descaling of steam generator, shorter CleanJet+Care process). The entire content of the steam gen-The entire content of the steam gen-
erator is pumped into the quenching box.
Above 4% scale the Descaling tab (starting of descaling program)
will be shown under Service.
The customer will be informed that soon a descaling
will be needed. This information can be quitted.
Reaching 16% the customer will be informed that descaling
is urgently needed. This information will be active for 2 minutes
Possible error messages during CleanJet +Care
Problem Cancel error indication by:
Step 1: Service 10 SC pump Follow fault tree
Step 2: Low water Y1, water tap Solve reason for low water
indication (water tap etc)
Step 3: Service 41 Y3, moistening blocked (CDS) Rinse without tabs
Step 4: Service 42 Y4, care valve blocked (CDS) Rinse program
Step 5: Service 43 Y1, Y3, Y4 valve leaking (CDS) Rinse program
Step 12: Service 40 Care pump, Care hose Rinse program
Step 13: Service 110 SC pump, level electrode Abort program
Step 14: Service 120 Care pump, level electrode Abort program
Step 15: Service 44 Steam heating (B1) Rinse program
An interrupt of the CleanJet processes is possible.
The duration of the following interrupt program is approximately 27 minutes.
The cabinet will be flushed with CleanJet pump M6. Tthe steam generator will be filled with the Care
valve Y4. Then the steam generator will be emptied with SC Pump M4 and then overfilled with the
solenoid valve filling Y1. Now the steam generator will be emptied once again with SC Pump M4 and
then refilled. Finally there is a short steam phase (neutralisation of the steam generator).
CleanJet interrupt program
Should a running CleanJet program be interrupted by power failure or the unit has intentionally been
switched off, an ABORT program of approx. 27min must be started to bring the unit back into safe
operation mode. This ABORT program can not be shortened or aborted again but must be completed
successfully.
Service