8 Rockwell Automation Publication 440R-UM010C-EN-P - September 2016
Chapter 1 Overview
Function 2 - E-stop
Function 2 is used for E-stop applications. The production process requires an
orderly shutdown. Some processes must be stopped immediately and some
must be stopped shortly thereafter. To initiate the stop, you press an E-stop
button. The GLT safety relay initiates an immediate stop command followed
by a delayed stop command.
Figure 2
shows some of the key hardware features of the GLT safety relay.
Figure 2 - GLT Hardware Details
8 Removable Terminals
5 Status Indicators
3 Multi-position Rotary
Configuration Switches
8 Removable Terminals