Brief Instructions on Commissioning ET 200S
2-3
Distributed I/O System ET 200S
EWA 4NEB 780 6024-02 07
Requirements
You must have set up an S7 station consisting of a power supply module and a
DP master (for example, CPU 315-2 DP). A CPU 315-2 DP was used as the
DP master in this example. However, any other DP master (IEC 61784-1:2002
Ed1 CP 3/1) could be used instead.
STEP7 (as of V 5.0 with ServicePack 3) is fully installed on your programming
device (PG). You must be familiar with STEP7.
The programming device must be connected to the DP master.
Installation
1. Mount the rail (35 mm x 7.5 mm or 15 mm) with a length of at least 210 mm on
a solid base.
2. Install the various modules on the rail beginning on the left (hook on, swing in,
move to the left). Adhere to the following sequence:
IM151-1 STANDARD interface module
TM-P15S23-A1 terminal module
4 x TM-E15S24-A1 terminal module
TM-P15S23-A1 terminal module
4 x TM-E15S24-A1 terminal module
Terminating module
3. Set the PROFIBUS address 3 on the IM 151-1 STANDARD interface module.
64
32
16
8
4
2
1
ONOFF
PROFIBUS address 3
Figure 2-2 Setting the PROFIBUS Address 3