See also
Commissioning after storage (Page 36
)
4.13.6 Storage for between two and four years
If machines are to be stored for between 2 and 4 years, then also observe the following:
When ordering, the manufacturer must know the storage time.
4.13.6.1 Grease caps
Grease caps must be available at the shaft outlet and at the terminal box cover. Do not rotate
the machine shaft before commissioning as the protective grease coating will be destroyed. If
rotating parts have to be turned, then apply a new protective coating of grease.
4.13.6.2 Commissioning
Remove the moisture-absorbing substance, such as Branogel, from the terminal boxes
before commissioning.
See also
Commissioning after storage (Page 36)
4.13.7 Storage at low temperatures
4.13.7.1 Storing machines at temperatures down to -50° C
If machines are stored at temperatures of down to -50° C, then also take into account the
following:
The normal roller bearing grease of machines is suitable for operating temperatures of
between -30 °C and +130° C. Temperatures down to ‑50° C are harmless for the roller
bearing grease if the machine is non operational or is in storage.
For operation at -50 °C, the bearings have a special grease, e.g. Aeroshell Grease 7.
Machines with regreasing system must be regreased when commissioning. Double the
amount of grease that is specified on the lubricant plate.
4.13.7.2 Regreasing system
Machines with regreasing system must be regreased when commissioning. Double the
amount of grease that is specified on the lubricant plate.
Preparations for use
4.13 Transport and storage
LOHER CHEMSTAR 1PS2
34 Operating Instructions 08/2016