5.3 Preparations for installation
5.3.1 Requirements for installation
The following requirements must be satisfied prior to starting installation work:
Staff have access to the operating and installation instructions.
The machine is unpacked and ready for mounting at the installation location.
Note
Measure the insulation resistance of the winding before starting installation work
Wherever possible, measure the insulation resistance of the winding before starting
installation work.
If the insulation resistance lies below the specified value, take appropriate
remedial measures. These remedial measures may necessitate the machine being
removed again and transported.
NOTICE
High temperatures
The motor components get very hot during operation. High temperatures can damage
mounting parts such as the cable insulation.
Temperature-sensitive parts such as normal cables or electronic components must not
rest against or be attached to mounted machine parts.
Only use heat-resistant mounting parts. The connecting cables and cable entries must be
suitable for the ambient temperature.
5.3.2 Safety information – do not lift below -55°C
WARNING
Lifting at temperatures below -55°C
The
welding
material of the lifting posts or the support ribs themselves can become brittle at
temperatures below -55°C. When lifting and transporting, the support ribs can tear off and
the motor might be dropped.
This can result in death, serious injury or material damage.
Only lift the machine using the support ribs at temperatures above -55° C. Alternatively, warm
up the support ribs or lift the machine in a different way.
Assembly
5.3 Preparations for installation
LOHER CHEMSTAR 1PS2
40 Operating Instructions 08/2016