Start-up
7
When carrying out any work on the machine, observe the general safety instructions and the
specifications contained in EN 50110‑1 regarding safe operation of electrical equipment.
See also
Safety information (Page 13)
Note
Service Center
Please contact the Service Center
(Page 117), if you require commissioning support.
7.1 Checks to be carried out prior to commissioning
Once the system has been correctly installed, you should check the following prior to
commissioning:
Note
Checks to be carried out prior to commissioning
The following list of checks to be performed prior to commissioning does not claim to be
complete. It may be necessary to perform further checks and tests in accordance with the
specific situation on-site.
The machine is undamaged.
The machine has been correctly installed and aligned, the transmission elements are
correctly balanced and adjusted.
All fixing screws, connection elements, and electrical connections have been tightened to
the specified tightening torques.
The operating conditions match the data provided in accordance with the technical
documentation, such as degree of protection, ambient temperature, etc..
Moving parts such as the coupling move freely.
All touch protection measures for moving and live parts have been taken.
The machine is undamaged.
The machine has been correctly installed and aligned, the transmission elements are
correctly balanced and adjusted.
All fixing screws, connection elements, and electrical connections have been tightened to
the specified tightening torques.
LOHER CHEMSTAR 1PS2
Operating Instructions 08/2016 65