Accessories
3.10 Accessories for integration in the power distribution equipment
3WJ Air Circuit breakers
Operating Instructions, 12/2022, L1V30828903001-01
149
Preparatory work
Open the Circuit Breaker and discharge the stored energy spring.
Disconnect auxiliary circuits.
Rack the Circuit Breaker to maintenance position and remove from the guide frame.
See chapter Preparation for maintenance work (Page 178)