3.10 Accessories for integration in the power distribution equipment
3WJ Air Circuit breakers
164 Operating Instructions, 12/2022, L1V30828903001-01
Installation - Frame size II
Screw the clips to the upper and bottom location of the guide frame. Only hand tighten
the screws.
Insert the phase barrier, which is fixed in the correct position when you hear the "click"
sound.
The audible clicking into place ensures that the upper and lower hole of the phase barrier
are positioned correctly within the clip.
Then fasten the screws of the clips with 8 Nm torque.