EasyManuals Logo

Siemens siprotec 7SD5 User Manual

Siemens siprotec 7SD5
698 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #130 background imageLoading...
Page #130 background image
2 Functions
130
7SD5 Manual
C53000-G1176-C169-1
be useful (address 1901 PROGAM U/I = LE:Uphe/LL:Uphe), accepting lesser sen-
sitivity for earth-free faults, since the overcurrent stage Iph>> usually picks up there.
In networks with low–resistance earthed starpoint, the U/I/ϕ pickup should only
come into effect on earth faults as phase-to-phase faults are detected by the overcur-
rent pickup. In this case it is reasonable to set address 1901 PROGAM U/I =
LE:Uphe/LL:I>>.
In isolated or resonant-earthed power systems it is possible to control the U/I/Ï•
pickup using phase-to-phase voltages only (address 1901 PROGAM U/I =
LE:Uphp/LL:Uphp). Naturally, this excludes pickup by single earth faults, however,
it also does not allow a correct double earth fault detection, therefore it is suitable only
for small isolated cable networks.
Two further general settings refer to the final times, i.e. the tripping times in a worst
case scenario for faults outside all distance zones. They should be set above the delay
times for distance zones providing a final back-up option (see also configuration of the
function settings for the distance zones in Section 2.5.2.2).
The directional final time DELAY FORW. PU (address 1902) only works with short-
circuits in forward (line) direction if there is no impedance within a distance zone after
pickup.
The non-directional final time DEL. NON-DIR PU (address 1903) works for all faults
if there is no impedance within a distance zone after pickup.
Overcurrent Pickup The maximum operational load current that can occur is crucial for the setting of over-
current pick-up. Pickup due to overload must be ruled out! Therefore the pickup
value Iph>> (address 1910) must be set above the maximum (over-)load current that
is expected (approx. 1.2 times). In this case, it must be ensured that the minimum fault
current is above this value. If this is not the case, U/I pickup is required.
Calculation Example
:
Maximum operational current (incl. overload) is 680 A, for current transformers 600
A/5 A, minimum short circuit is 1200 A. The following settings are made:
Iph>> = I
L max
· 1.2 = 680 A · 1.2 = 816 A
This value is sufficiently below the minimum short-circuit current of 1200 A. When con-
figuring via PC and DIGSI
®
this value can be entered directly as primary value. The
conversion to secondary values is
The condition for minimum short-circuit current also applies to earth faults (in the
earthed network) or for double earth faults as long as overcurrent pickup is solely
used.
U/I(/Ï•) pickup If U/I pickup is required because the minimum short-circuit current is below the
maximum load current (incl. a safety factor of 1.2), the condition for maximum load
current in respect to Iph>> still has to be observed. Then, the minimum current limit
Iph> (address 1911) is set to below the minimum short-circuit current (approx. 10 %).
This also applies to the phase currents during earth faults or double earth faults.
In address 1930 1ph FAULTS you can choose whether a phase-to-earth loop shall
be selected in an earthed network during single-phase pickup without earth current (I
E
release). The setting 1ph FAULTS = PHASE-EARTH is useful if no or only little earth
current can flow via the measuring point in the event of earth faults. With 1ph FAULTS
www . ElectricalPartManuals . com

Table of Contents

Other manuals for Siemens siprotec 7SD5

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens siprotec 7SD5 and is the answer not in the manual?

Siemens siprotec 7SD5 Specifications

General IconGeneral
BrandSiemens
Modelsiprotec 7SD5
CategoryRelays
LanguageEnglish

Related product manuals