Mounting and Commissioning
3.3 Commissioning
SIPROTEC, 7SD5, Manual
C53000-G1176-C169-5, Release date 02.2011
549
Figure 3-29 Local measured values in the WEB-Monitor - Examples of plausible measured values
Figure 3-30 Remote measured values in the WEB-Monitor - Examples of plausible measured values
Polarity check
If the device is connected to voltage transformers, the local measured values already allow a polarity check.
If there are more than two ends, one current path is still tested first. A load current of at least 5 % of the rated
operational current is still required. Any direction is possible, but it must be known.