Section 4 – Inspections Before Operation Visual and daily maintenance inspections
4.2-5 Base
Do the inspection that follows, and make sure:
1
Base weldment
There are no cracks in the welds or structure.
There are no signs of deformation.
2
Steer cylinder assembly
The steer cylinder assembly is correctly
installed.
There are no loose or missing fasteners.
There is no visible damage.
3
Greasing points
There is no visible damage.
There is no dirt or obstructions.
4
Drive axles
There are no loose or missing parts.
All the fittings and hose connections are tight.
There is no sign of hydraulic leakage.
5
Tie rod
There are no loose or missing parts.
The tie rod end studs are attached and tight.
There is no visible damage.
6
Ladder
There are no loose or missing parts.
There is no visible damage on the left and right
MEWP ladders.
7
Outriggers (optional equipment)
There are no loose or missing parts.
There is no visible damage.