7 Commissioning
SMA Solar Technology AG
Operating manualEVCxx-10-BE-en-1034
7 Commissioning
7.1 Commissioning Procedure
This section describes the commissioning procedure and gives an overview of the steps you must
perform in the prescribed order.
Procedure See
1. Commission the product. Section7.2, page34
2. Establish a connection to the user interface of the product.
There are various connection options to choose from for
this:
Direct connection via WLAN
Connection via WLAN in the local network
Connection via Ethernet in the local network
Section8.1, page38
3. Change the network configuration, if necessary. The auto-
matic network configuration recommended by SMA Solar
Technology AG via DHCP server is activated by default.
Section7.3, page36
4. Carry out the configuration using the installation assistant. Section7.4, page36
5. To monitor the system in the Sunny Portal and view the
data visually, create a user account in the Sunny Portal
and create a system in the Sunny Portal or add devices to
an existing system.
https://www.sunnypor-
tal.com
7.2 Commissioning the Product
Requirements:
The product must be correctly mounted.
Procedure:
1. Place the enclosure lid slightly tilted on the terminal
cover and then close it completely.
30°
~