2| INSTALLING YOUR SMART BOARD 685IX PREMIUM INTERACTIVE
WHITEBOARD SYSTEM (APPLIANCE-BASED)
– Installing SBA speakers and cables on page 8
– Installing additional cables on page 9
– Installing the UX60 projector on page 9
– Securing the cables on page 10
– Installing the control module cable on page 11
– Mounting the interactive whiteboard on page 11
• Completing your installation on page 12
– Aligning your interactive whiteboard with the projector on page 12
– Installing the control module on page 13
– Installing the pen tray on page 13
– Configuring the projector to turn on or off on page 14
– Configuring the hub to control the projector on page 14
– Orienting your interactive whiteboard system on page 15
Before installing the SMART Board 685ix
interactive whiteboard system
Environmental requirements
Before installing your system, refer to the environmental requirements in the SMART
Board™ 685ix Interactive Whiteboard System Configuration and User’s Guide,
document 99-00984-20, provided with your system.
Verify the installation of the FUWM-600 wall mount and the
SMART Hub SE240/VE220
You must complete the installation of the FUWM-600 wall mount and the SMART Hub
SE240 or VE220 before you can install the UX60 projector, the SMART Board 685
interactive whiteboard and the control module. Refer to the FUWM-600 SE240/VE220
installation guide, document 99-01032-20, provided with your FUWM-600 wall mount
unit for more information.
NOTE
Because you can install the SMART Board 685ix interactive whiteboard system in
several configurations, several components included with the system, such as the
Extended Connection Panel (ECP), remain unused when you complete the
installation outlined in this guide.