EasyManuals Logo

SolarEdge SE100K User Manual

SolarEdge SE100K
105 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #21 background imageLoading...
Page #21 background image
Cordless drill (with a torque clutch)or screwdriver and bits suitable for the surface
on which the inverter and Power Optimizers are installed and for opening the Safety
Unit drill guides. Use of an impact driver is
not
allowed
Ring terminals crimping tool
Wire cutters
Wire strippers
Voltmeter
For installing the communication options, you may also need the following:
For Ethernet:
CAT6 twisted pair Ethernet cable with RJ45 connector
If using a CAT6 cable spool: RJ45 plug and RJ45 crimper
For RS485 / CAN Bus :
Four- or six-wire shielded twisted pair cable
Watchmaker precision screwdriver set
Installation Procedure
The following procedures, are required for installing and setting up a new SolarEdge
site. Some of these procedures also apply to modification of an existing site.
1. Installing the Power Optimizers
2. Installing the Synergy Manager and Synergy Units
3. "Connecting PV Modules and AC to the Synergy Manager" on page47
4. Connecting AC and PV Strings to the Synergy Manager
5. Activating, Commissioning and Configuring the System
6. Setting Up Communication with the Monitoring Platform
Three Phase Inverters with Synergy Technology PN: SExxK-xxxxIxxxx
20 Installation Procedure

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SolarEdge SE100K and is the answer not in the manual?

SolarEdge SE100K Specifications

General IconGeneral
Max. Efficiency98.8%
Transformer-lessYes
Protection RatingIP65
Frequency50/60 Hz
AC Output Power100 kW
Rated AC Power100, 000 W
Maximum DC Power135000 W
AC Voltage400 V
Max. Input Voltage1000Vdc
Operating Temperature Range-25°C to 60°C

Related product manuals