Verifying the Connection
After connecting and configuring a communication option, perform the following steps
to check that the connection to the Monitoring platform has been successfully
established.
1.
If the Synergy Manager cover is not closed, close it: Attach the cover and secure it by
tightening the screws of 2.6 lb.*ft. For proper sealing, first tighten the corner screws
and then the two central screws.
2. Commission the inverter as describe in "Activating, Commissioning and
Configuring the System" on page75.
3. Access SetApp and selectStatus from the Configuring screen.
4. In the Summary section, under Server Comm., make sure S_OK is displayed
together with the selected communication option.
5.
Scroll down to the Communication section and check that the communication
options are as required.
Three Phase Inverters with Synergy Technology PN: SExxK-xxxxIxxxx