EasyManua.ls Logo

SolarEdge SE100K - Connecting PV Strings to the Synergy Manager

SolarEdge SE100K
105 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Connecting PV Strings to the Synergy Manager
CAUTION!
The PV inputs of the inverter are not intended for connection to a battery or any
other type of DC source except a PV array.
CAUTION!
When installing a system with more than three strings per a single Synergy Unit
(Whether connected directly or via a combiner box), fuses are required. In
SolarEdge system, 25A fuses shall be used.
To connect the DC wires to a Synergy Manager with spring-clamp DC terminals:
NOTE
Use copper aluminum wires with insulation rated for at least 90°C. Make sure
to consider the maximum termination temperature at both ends of the
conductor and to base the ampacity on the lower value.
1.
Thread a 6 to 12 AWG wire through the AC conduit.
2.
Strip 0.7" (18 mm) of wire insulation from the end of the wire.
NOTE
When using a stranded wire, use of ferrule is at the installer discretion
3.
Insert the DC conduit into the DC-side opening at the bottom left-side of the
Synergy Manager and fasten the conduit nut.
Three Phase Inverters with Synergy Technology PN: SExxK-xxxxIxxxx
52 Connecting PV Strings to the Synergy Manager