Information
From the Commissioning menu, select Information to view and set various system
settings, as described below.
CPU Version: The communication board firmware version
DSP 1/2 Version: The digital board firmware version
NOTE
Please have these numbers ready when you contact SolarEdge Support.
Serial Number: The inverter serial number as appears on the enclosure sticker
Error Log: Displays the last five errors, and enables resetting (clearing) the log
Warning Log: Displays the last five warnings, and enables resetting (clearing) the
log
Step 3: Verifying Proper Activation and
Commissioning
1. Select Information and verify that the correct firmware versions are installed on each
inverter.
2. Select Status and verify that inverter is operating and producing power (see also
Viewing System Status
on page 37).
3. Verify that additional configurations were properly set by viewing the relevant
Status screens.
4. Verify that the green inverter LEDis steadily lit.
Your SolarEdge power harvesting system is now operational.