To verify proper power optimizer connection:
Measure the voltage of each string individually before connecting it to the other
strings or to the inverter. Verify correct polarity by measuring the string polarity with a
voltmeter. Use a voltmeter with at least 0.1V measurement accuracy.
NOTE
Since the inverter is not yet operating, you may measure the string voltage
and verify correct polarity on the DC wires inside the Connection Unit.
For troubleshooting power optimizer operation problems, refer to
Power Optimizer
Troubleshooting
on page 78.
-Three Phase Inverter with Synergy Technology Installation MAN-01-00402-1.2
20 Step 4: Verifying Proper Power Optimiser Connection