EasyManuals Logo

SOLIS 5G Series User Manual

SOLIS 5G Series
38 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #19 background imageLoading...
Page #19 background image
17
4.Installation
Figure 4.16 Three phase four lines connect via CT
L1
L2 L3
Ia* Ia Ib* Ib Ic* Ic
N
L1
L2
L3
To detect the backflow power, the CTs need to be installed at the PCC
(Point of Common Coupling), instead of the load branch circuit.
NOTE:
For three phase system, CT must be installed on U,V and W with correct
sequence, otherwise EPM can not detect the correct data.
The CT cable outer diameter is 6.5mm-7.5mm, cross-sectional area 1.5mm².
a. Switch off the main switch, disconnect the line cables.
b. Insert the cables through the CT, make sure the P1 on CT is towards grid and P2 is
towards the inverter.
c. Reconnect the line cables.
4.3.4 Connect and fix the CT
NOTE:
If the CT is installed in the wrong direction, the EPM can't work normally.
NOTE:
The CT must be grounded on the secondary side.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SOLIS 5G Series and is the answer not in the manual?

SOLIS 5G Series Specifications

General IconGeneral
BrandSOLIS
Model5G Series
CategoryController
LanguageEnglish

Related product manuals