2. Put the copper wire of the cable splitter into the plug terminal and tighten the screw.
Figure 4.15
3. Insert the sleeves assembly into the plug then lock it with a buckle, tighten the lock nut
and the torque is 3.5-4N.m.
Figure 4.16
Figure 4.17
Figure 4.18
4.3.3 External ground connection
An external ground connection is provided at the right side of inverter.
Prepare OT terminals: M4. Use proper tooling to crimp the lug to the terminal.
Connect the OT terminal with ground cable to the right side of inverter. The torque is
20 in-lbs (2Nm).
Figure 4.20 Connect the external grounding conductor
4. Connect the AC grid connector to the inverter, until hearing a slight click sound that
indicates the connection succeed.
Figure 4.19 Connect the AC Connector to the Inverter
Note: Connection for Split phase grid.
When connect to 208/220/240V split phase, please connect L1 to “L” terminal,
L2 to “N” terminal. Also connect earth to ground terminal.