5. Operation after overload and shutdown
Warning
After the crane stops automatically due to overload, the following crane operations are prohibited.
These operations may cause the machine to overturn or the frame to break, which is very dangerous.
Boom lowering operation.
Boom extension operation.
Lifting operation of hook.
Crane slewing operation.
Recovery operation after overload shutdown
The overload recovery operation should perform the following actions:
1. Lower the hook. Lower the hook and place the lifted load on the ground.